Site search
sponsored by
Sierra Sun | Lake Tahoe/Truckee News and Information
 
Sierra Sun | Lake Tahoe/Truckee News and Information
Sierra Sun | Lake Tahoe/Truckee News and Information
Welcome, Guest  avatar

Please enter the following information:

Email or Screen Name:
Password:
  Remember Me
 
  Forgot Password?
  Didn't receive your verification email?
  Become a Member
Sierra Sun | Lake Tahoe/Truckee News and Information
Jobs
Sierra Sun | Lake Tahoe/Truckee News and Information
Real Estate
Sierra Sun | Lake Tahoe/Truckee News and Information
Classifieds
Sierra Sun | Lake Tahoe/Truckee News and Information
Search for homes by MLS, classified listings, rentals, and much more!

Sierra Sun | Lake Tahoe/Truckee News and Information
Home  >   > 
<< back
Tuesday, May 27, 2008

More on the Mousehole



Print Comment
In the face of enormous costs to rebuild the Mousehole into a bridge, the Town of Truckee is looking at different tunneling options.

The Highway 89 south undercrossing of the Union Pacific Railroad has been a high priority for the Town of Truckee, who, working with Caltrans, wants to make a safer route for cyclists and pedestrians through the tunnel.

“If we can avoid the cost of the shoofly (a temporary bridge to re-route train traffic while building a new bridge) we could save millions of dollars, so we are trying to make the tunnels work,” said Dan Wilkins, director of public works.

Previous estimates for building a new bridge were between $46 and $52 million, with the temporary bridge alone costing $10 to $15 million, Wilkins said.

“What we would have engineers looking at would be three tunnels built in phases,” Wilkins said.

The first phase would be a pedestrian and cyclist tunnel to the east of the existing Mousehole, separating those users from motor vehicle traffic, he said.

Then, a second tunnel to the west of the existing Mousehole would take southbound traffic out of the existing roadway, leaving the Mousehole dedicated to northbound vehicles, Wilkins said.

With those two complete, the town and Caltrans could replace the Mousehole itself with a bigger, newer tunnel.

The project could be completed without ever disturbing train operations, Wilkins said.

Along with the decrease in cost, Wilkins said there would be less environmental impact during construction, notably to Donner Creek to the east, just before it empties into the Truckee River.

The town will meet with Caltrans in June to discuss the potential change in plans, Wilkins said.

$2.8 million in federal money has been earmarked for the Mousehole project.

— Greyson Howard Sierra Sun


facebook Print
Ads by Google
Other Top Items
Related Articles
Most Recommended Articles
downloading content
Comments
Previous Guide Line
Next Guide Line
Sort comments by:
About Us | Staff | Site Map | Privacy Policy | Terms of Use | Swift Communications