Lake Tahoe route 28 project on schedule to finish Friday

Sun Staff Report

INCLINE VILLAGE, Nev. ” The $5 million State Route 28 resurfacing project between Sand Harbor and the U.S. Route 50 intersection is on schedule and will be fully finished by 5 a.m. Friday, a Nevada Department of Transportation Spokesman said Wednesday.

The project had completely shut down the 8-mile path between 7 p.m. Sunday and 5 a.m. Friday the past three weeks, starting May 3.

The project saw no delays during the three-week closure, said NDOT’s Scott Magruder.

The projects second phase involves one lane of traffic control from May 22 to July 2 on State Route 28 from Sand Harbor to the East Lakeshore Boulevard intersection. Motorists can expect half-hour delays during Phase 2, although it also plans to keep the road open without delays on the weekend.

If Granite cannot finish phase two by July 2, in time for the Fourth of July Weekend, Magruder said NDOT will levy a $15,000-per day fine against the contractor until work is completed.


Support Local Journalism

 

Support Local Journalism

Readers around Lake Tahoe, Truckee, and beyond make the Sierra Sun's work possible. Your financial contribution supports our efforts to deliver quality, locally relevant journalism.

Now more than ever, your support is critical to help us keep our community informed about the evolving coronavirus pandemic and the impact it is having locally. Every contribution, however large or small, will make a difference.

Your donation will help us continue to cover COVID-19 and our other vital local news.

For tax deductible donations, click here.

Start a dialogue, stay on topic and be civil.
If you don't follow the rules, your comment may be deleted.

User Legend: iconModerator iconTrusted User